TRAZTRU Platform Deployment Timeline

Tasks & Phases
Month 1
Month 2
Month 3
Month 4
Month 5
Month 6
Month 7
Month 8
Phase 1: Foundation
Core TRAZTRU platform deployment
Platform Setup
User role setup and access control
Access Control
PDPA consent framework activation
PDPA Framework
Basic farmer registration and plot mapping
Farmer Registration
Phase 2: Enhanced Features
2FA authentication system deployment
2FA System
Advanced mobile app with offline capabilities
Mobile App
Product conversion factor system setup
Conversion System
Collection center and mill integration
Integration
Phase 3: Advanced Analytics
GHG calculation engine implementation
GHG Engine
Risk assessment and due diligence reporting
Risk Assessment
Customer relationship management activation
CRM System
Transportation and logistics module integration
Logistics
Phase 4: Testing and Go-Live
Comprehensive system testing and validation
Testing
User training and change management
Training
Performance optimization and tuning
Optimization
Full operational deployment and handover
Go-Live
Phase 1: Foundation
Phase 2: Enhanced Features
Phase 3: Advanced Analytics
Phase 4: Testing & Go-Live
Total Project Duration: 8 Months | Phases: 4 Sequential Phases | Delivery: Incremental Implementation